Kehewin, Alberta
KCN Water Distribution Line - Phase 2
About this Project
Kehewin Cree Nation sponsored an upgrade of the existing water treatment plant and provided water services to 68 residences. Option worked with the Nation to find cost savings of $2.5 million, providing an opportunity to expand the project scope to include additional phases (2B, 2A and Hwy 41). Option also participated in the pilot program for Pehta, a new financial reporting tool for First Nations.
Construction Particulars
- Laydown and site preparation (clearing, grubbing and electrification)
- 200mm water main installation (10.5 km) via HDD and two tie ins to the existing infrastructure
- Upgrades to the water treatment plant, including distribution pump system upgrade
- 68 residential service connections of 40mm pipe via HDD, one trickle feed system installation, the decommission of 70 residential cisterns
- Installation of air release valves (17), gate valves (13), and blow offs (5)
- Extra work: Ph 2B 200mm water main installation via HDD (2.7 km) and service connections across Ph 2B, 2A and Hwy 41